Out of the ground
Today we poured the slab. 56 cubic metres of concrete took less than 6 hours to pour and finish. Check out the photos of the pour on our flickr account.
Our intentions are now to let the slab slowly cure by keeping it as wet as possible over the next 7 days which largely will be done by the rain that has been forecast. We will then let it sit at least 4 weeks to reach maximum strength before we start on the walls. Until then we are going to start on the power room so we have a secure place to store tools on site.