Finally on the downwind stretch

After a good spell of fine weather last week our completed percentage for the walls is now 52%.

We are about 200 blocks away from reaching level 7 around the perimeter and getting all sections to this is the next goal. From there the verandah tie downs are moulded into the wall, using laser levelling for accuracy. Once that is done there are only 170 blocks left to complete the walls!